Less than two weeks before it was announced that work to restart Whyalla Steelworks’ Blast Furnace No.2 was being abandoned OneSteel Manufacturing Pty Limited’s (OneSteel) Committee of Inspection (COI) was told progress in a critical step in the furnace’s restoration was only a week from completion.
“Ultimately the decision was made today to close the blast furnace primarily for safety reasons and also in consideration of the long-term future of OneSteel given the practical reality that there is now a very limited chance of a recovery being achieved.” KordaMentha partner Lara Wiggins, September14, 2026.
Minutes of the most recent meeting of the OneSteel COI held on September 3 disclose that when Australian Workers Union (AWU) representative Shane Karger asked when installation of six fuel nozzles called tuyeres (pronounced tweers) would be complete administrator Sebastian Hams said the estimate was about a week.
Being no fool, Hams added that that estimate was conditional on there being no unforeseen delays.
What wasn’t contained in the September 3 meeting Minutes was that bringing the old and decrepit blast furnace back to full function was proving impossible.
iNO asked Wiggins and Hams whether they had received new information about the blast furnace restoration projection after the September 3 COI meeting and if so, was that information provided following a request from the administrators and if not, how did they arrive at their decision to cancel the project.
A spoken for the administrators told iNO that no new information had been received. Ultimately he said those tasked with restarting to the furnace had never been able to get more than two tuyeres functioning properly when six were required simply to generate sufficient heat to get the furnace to stage one of operation.
While this detail may well be in the transcript of the September 3 meeting it does not appear in the Minutes.
The spokesman also said that Blast Furnace No.2 has 18 tuyeres in total and all have to be functioning for the furnace to operate properly.
Despite the efforts of various engineers trying different plans he said successful operation evaded them and that each attempt carried risks to those involved, raising the safety concerns that ultimately led the administrators to permanently shut the plant.
On September 14, 11 days after a meeting at which no hint of the difficulties was seemingly provided, the administrators announced that the restoration project was at an end because it was unsafe to continue.
Why these safety issues weren’t identified before the costly restoration project was commenced wasn’t answered, perhaps because none of the COI members thought to ask and the administrators didn’t anticipate them.
In an affidavit dated September 14 and filed in the Federal Court joint administrator and KordaMentha partner Lara Wiggins deposed that while safety issues were the primary reason informing the administrators’ decision to cancel restoration efforts they had also taken into account the threat the ageing furnace could pose to whoever KordaMentha finds to buy the business.
“Ultimately the decision was made today to close the blast furnace primarily for safety reasons and also in consideration of the long-term future of OneSteel given the practical reality that there is now a very limited chance of a recovery being achieved,” Wiggins said in her September14, 2026 affidavit.
Clearly the decision benefits the administrators in that the related mining and port operations make a much more attractive package of assets to sell when the deal no longer requires a buyer to take on the millstone that a 60 year old and poorly maintained blast furnace represents.
And the sovereign-backed indemnity of $1 billion provided by the SA State and Federal Labor governments means the veritable slag heap of wasted hours accumulated by the administrators and advisors can be charged to taxpayers despite the project seemingly being doomed from commencement.


Be the first to comment on "Blast furnace restoration doomed from the beginning"